Ain Sokhna Desalination Plant

Client: Ministry of Defense of  A.R.E.
Duration: 2018 - 2023
Value: USD 100,000,000

Project Description

Desalination plant 236,000 m3/day developedin 4 phases.

• 64,000 m3/dayforindustrial use

• 170,000 m3/daypotable wáter

Scope of Work

  • Detailed Process and Engineering Design

  • Procurement

  • Construction

  • Installation

  • Commissioning

  • Operation and Maintenance for 15 months

Ain Sokhna Desalination Plant
Sewer Inspection & Cleaning Services Framework

Sewer Inspection & Cleaning Services Framework

Client: ASHGHAL
Duration: 2016 - 2021
Value: QAR 188,212,588.86

Project Description

  • SIC_001:Inspection and Cleaning Services to the Foul Sewer Network –Area B

  • SIC_008:FS Preventive Maintenance Programme Package 6 – Area E

  • SIC_009:FS Preventive Maintenance Programme Package 2 – Area A2

  • SIC_018:Foul Sewer Lining Refurbishment Works

  • SIC_019:Rising Main Condition Survey, Rehabilitation and Works

  • SIC_029:FS Network Area Preventive Maintenance Programme – CCTV Survey of FS Network Assets

  • SIC_030:FS Network Area Preventive Maintenance Programme Network Lining (Phase 1)

Scope of Work

  • The inspection, cleaning and report related services to any Authority operated (FS) and (SGW) network asset(s) in the State of Qatar.

  • Any new assets added to the Authority’s FS, SGW and SW network during the Framework Contract period.

  • The provision of all sufficient labour, supervision, vehicles, tools, materials, chemicals, consumables, equipment, supplies, spare parts, emergency equipment, Approved Supplier workshop(s) and testing, incidental engineering, and transportationnecessary for the completion of the Works.

  • Planned, preventive and reactive Inspection and cleaning activities, disposal of waste and Waste Products, bypass pumping and traffic management.

  • Condition assessment surveys.

  • Water sampling, quality testing &analysis at the Site.

  • The completing of records and reports throughout the period of each Work Order which shall be available for the Authority’s computerized management system.

Ras Sedr Desalination Plant

Client: Egyptian Armed Forces
Duration: 2019 - 2020
Value: USD 30,000,000

Project Description

Seawater Desalination plant
30,000 m3/daywith 6 RO skids

Scope of Work

  • Detailed Process and Engineering Design

  • Procurement

  • Construction

  • Installation

  • Commissioning

  • Operation and Maintenance for 15 months

Ras Sedr Desalination Plant

RLTO Expansion And Offplot Facilities Of Thenorth Field Expansion Project (Epc-3) .
Civil Works

Client: Qatar Energy
Duration: 2023 - 2025
Value: QAR 110,872,320.20

Project Description

All civil works related to construction of New Gas Plant at EPC-3 including but not limited to (they should be in bullet points): Shallow and Deep Excavation up to 6 m, 800 m of Pipeline Laying, Earthworks, Backfilling, Concrete works, Installation of  various Precast elements

RLTO Expansion And Offplot Facilities Of Thenorth Field Expansion Project (Epc-3) .

Construction Of Flood Prevention Scheme 
(FPS-Phase 3) Of Doha North Areas C850/1

Client: ASHGHAL
Duration: 2022 - 2024
Project: QAR 36,878,097.40

Project Description

The project C850/1 aims to solve the flooding issues for approximately 97 hotspots in different area within Doha, Daayen Rayyan muncipalities.

The works addressed by the project compries design, supply execution, testing and completion of surface water network,surface water netwroks, storgae tank, pumping station, and emergency flood areas as well as remediation of defects of existing surface water network.

Construction Of Flood Prevention Scheme (FPS-Phase 3) Of Doha North Areas C850/1
Catchment Zone Framework, Framework_ Qatar North

Catchment Zone Framework, Framework_ Qatar North

Client: ASHGHAL
Duration: 2021 - 2027
Value: QAR 126,059,160.22

Project Description

CZF_014:SGW Renewal Programme and Assets Improvement in Qatar – Qatar North


CZF_015:SGW Renewal Programme and Assets Improvement in Qatar – QatarSouth


CZF_027: Demolition Of Decommissioned Facilities - Phase 5


CZF_030:Foul Sewer Refurbishment in Qatar North Lining


CZF_031:Foul Sewer Refurbishment in Qatar South Lining

Scope of Work

  • Performing planned preventative, predictive and corrective maintenance, overhauling, mandatory control and certification of equipment, RRRU or enhancement of the site and associated systems of the CSI.

  • O&M including preventative, predicative and corrective maintenance.

  • Inspection, survey and cleaning;-  Repair, Replacement, Rehabilitation and Upgrading works

  • Customer service response

  • Emergency incident management, resolution and recovery

  • Network leakage and infiltration management

bottom of page